Chandrayaan-2: Many Changes Made To Flight Plan To Ensure 7 September Landing On The Moon
An illustration of the spacecraft's Earth-bound orbital manoeuvres
The 20-hour countdown to launch of the GSLV MK-III from Sriharikota will begin at 6.43 pm on Sunday
After the planned launch date for the Chandrayaan 2 mission was postponed by a week due to a technical fault in a fuel connecting joint in the GSLV MK-III rocket, it was also announced that there won't be any change in the planned landing date of the mission on the Moon.
As per the original mission timeline, the first 17 days after lift-off were dedicated to the 3,850-kg spacecraft entering its Earth-bound phase. This was when the orbiter-lander-rover composite would have been injected into an "Earth Parking Orbit" (170 x 38,000 km) to perform orbital manoeuvres crucial to the spacecraft escaping Earth's gravity. As this orbit-raising continued, the spacecraft will have needed to perform a "trans-lunar injection burn" (TLI) to send the spacecraft on its way to the Moon. The spacecraft will have made a total of five orbit-raising burns to reach its desired 150 x 1,41,000 km orbit.
The spacecraft would have then begun its coasting phase into an elliptical orbit about the Earth with an apogee (its furthest orbiting distance around the Earth) roughly equal to the radius of the Moon's orbit. The trans-lunar injection burn of the engines will need to be measured and timed to precisely target the Moon and match its revolution around the Earth for this movement.
A five-day cruise would have then followed when the Chandrayaan 2 composite travels the bulk of the distance between the Earth and Moon. Starting day 22 was a 3-day plan for lunar capture, with four Moon-bound burns of the engines to lower its orbit from the trans-lunar 150 x 18,000 km to a 100 x 100 km lunar orbit, where it will orbit for 28 continuous days collecting data.
ABOVE: Former and revised launch sequence for the GSLV-MK-III
BELOW: Former (left) and current (right) approach plan for Chandrayaan-2
After spending four weeks (28 days) in lunar orbit, the Vikram lander was to separate from the orbiter and enter a 30 x 100 km orbit, maintaining this orbit for four days. On D-Day (where D=descent), Vikram performs one final deorbit burn to kick off its descent, beginning its 15-minute-long pre-programmed landing sequence.
While a revised landing date hasn't been announced, it can be deduced from the stated information in the press release that the new landing date is 8 September. The Chairman of ISRO, Dr K Sivan, said that the agency intends to make up for some of the lost time in the orbit-raising segments of the mission, in an interview with the New Indian Express.
"The integrity of the mission is intact. Lander Vikram will touch down on Moon's surface as originally planned on September 6, which is crucial since the mission life of Vikram and rover Pragyan is only one Lunar Day (14 Earth days)," Sivan told the Express. "So, the travel time to Moon will be brought down from 54 days to 47 days. The mission has enough scope to make such an adjustment."